Capital Improvement Project (CIP)
Maintenance Tax Note (MTN)
St. Philip's College - MTN Renovation |
MTN Renovation Summary |
Campus |
Eastside Education and Training Center (EETC) |
Building |
E.E.T.C. |
Projected Construction Start |
May 2024 |
Projected Construction End |
August 2025 |
Campus |
Martin Luther King (MLK) Campus |
Building |
Center for Health Professions (CHP) |
Projected Construction Start |
August 2024 |
Projected Construction End |
May 2025 |
Campus |
MLK |
Building |
Center for Learning Resources (CLR) |
Projected Construction Start |
August 2024 |
Projected Construction End |
May 2025 |
Campus |
MLK |
Building |
Welcome Center (WEC) |
Projected Construction Start |
August 2024 |
Projected Construction End |
May 2025 |
Campus |
MLK |
Building |
Department of Public Safety (DPS) |
Projected Construction Start |
August 2024 |
Projected Construction End |
June 2025 |
Campus |
MLK |
Building |
Central Plant – Chiller |
Projected Construction Start |
September 2024 |
Projected Construction End |
May 2025 |
Campus |
MLK |
Building |
Center for Advocacy and Student Empowerment (CASE) |
Projected Construction Start |
October 2024 |
Projected Construction End |
August 2025 |
Campus |
MLK |
Building |
Maintenance |
Projected Construction Start |
August 2024 |
Projected Construction End |
November 2024 |
Campus |
MLK | ||
Building |
Applied Science Building (ASB) | ||
Projected Construction Start |
September 2024 | ||
Projected Construction End |
July 2025 | ||
Work on some classrooms and labs are expected to be completed in January 2025; medical offices and IT areas are expected to be completed in March 2025; automotive classrooms and shops are expected to be completed in April 2025; office areas are expected to be completed in June 2025. |
Campus |
MLK | ||
Building |
Child Development Center (CDC) | ||
Projected Construction Start |
May 2024 | ||
Projected Construction End |
July 2025 | ||
Phase 1A of the project is expected to be completed in September 2024; Phase 1B is expected to be completed in January 2025. |
Campus |
MLK | ||
Building |
Davis Science Building (SCI) | ||
Projected Construction Start |
September 2024 | ||
Projected Construction End |
August 2025 | ||
Level 1 of the project is expected to be completed in January 2025; Level 2 is expected to be completed in May 2025; and Level 3 is expected to be completed in October 2025. |
Campus |
MLK |
Building |
Health and Fitness Center (HFC) Demolition |
Projected Construction Start |
TBD |
Projected Construction End |
TBD |
Campus |
MLK |
Building |
Watson Fine Arts Center (WFAC): H-E-B Black Box Theater |
Projected Construction Start |
December 2023 |
Projected Construction End |
March 2025 |
Campus |
Southwest Campus (SWC) |
Building |
Diesel Technology Labs (DTL) |
Projected Construction Start |
June 2024 |
Projected Construction End |
November 2024 |
Campus |
SWC |
Building |
Multi-Disciplinary Instructional Center (MDIC) |
Projected Construction Start |
May 2024 |
Projected Construction End |
February 2025 |
Campus |
SWC |
Building |
Workforce Center for Excellence (WCE) |
Projected Construction Start |
September 2024 |
Projected Construction End |
March 2025 |